A public contract can be profitable on paper while leaving a small supplier short of cash. The supplier may need to buy stock, pay for transport and meet payroll before the procuring entity accepts the goods or pays the invoice. The larger the order relative to the supplier’s available cash, the more that timing matters.
Map the cash gap before bidding
Build a timeline from supplier deposits and stock purchases through delivery, inspection, acceptance, invoicing and collection. Place each expected outflow in the period it falls due. Put customer receipts in the period you realistically expect to collect them. Include existing obligations such as wages, rent and supplier payments so the forecast reflects the cash the business actually has available for the contract.
Track the lowest projected cash balance across the timeline. That point shows when the business may need additional funding. Run a second scenario in which acceptance takes longer or an invoice needs correction. If financing is needed, include its cost in the margin review and show the timing of principal repayments in the cash forecast.
Read the tender and contract together
Zimbabwe’s Public Procurement and Disposal of Public Assets Act [Chapter 22:23] provides the public procurement framework. For a particular supply contract, review the tender documents and signed terms to identify the delivery obligations, acceptance requirements, invoicing instructions and payment provisions. Raise material ambiguities through the tender’s clarification process before committing.
Check which event starts the contractual payment period and who can confirm it. Delivery, formal acceptance and receipt of a compliant invoice can happen on different dates. If the contract permits staged delivery, confirm whether each batch can be accepted and invoiced separately before putting staged receipts into the forecast. Include any security, retention or other cash commitment only where the tender or contract calls for it.
Track collection from the first delivery
Keep the purchase order or contract, delivery note, acceptance record and invoice together under one reference. Record the dates each document was submitted and acknowledged. Give someone responsibility for checking outstanding acceptance records, correcting invoice discrepancies and following up on overdue payments through the agreed channel.
Maintain the contractual due date and the current expected receipt date in separate fields. The first helps manage collections. The second gives finance a realistic basis for planning supplier payments and funding.
Worked example for a Zimbabwean school furniture supplier
A hypothetical small manufacturer wins an order to supply desks to a public institution. Its timber supplier requires a deposit before releasing materials. The manufacturer also needs to fund production wages and transport. In this example, the contract allows invoicing after formal acceptance, so a signed delivery note alone leaves the invoice milestone outstanding.
The finance team puts the deposit, wages and transport into the forecast before any contract receipt. It then moves the receipt later in a stress scenario to allow for an inspection delay. The largest funding gap occurs after the final delivery outlay and before collection. The cash tied up in the order also reduces what the manufacturer can commit to its other customers.
The team checks whether the agreed terms permit acceptance and invoicing by batch. If they do, it rebuilds the forecast using separate acceptance and receipt dates for each batch. If payment follows acceptance of the full order, it keeps the later receipt date and assesses whether supplier credit or available working capital can cover the gap. Production and finance agree who will obtain acceptance evidence and track the invoice.
The revised forecast gives management a basis for deciding whether it can fulfil the order while meeting its other commitments. It also shows whether funding costs leave enough margin to justify taking on a similar contract again.